Current Projects Status

Lemond Road Reconstruction - 13002

Location: Between Selby Avenue to Kim Lane SW.

Status: Bid Awarded

Start Date: May 2015

Completion Date:  9/1/2015

Low Bidder: James Brothers Construction Inc. - Elysian MN

Bid Amount:  $564,490.94

2015 Mineral Springs Parkway Reconstruction - 14001

Location:  Cherry Street NE to Mineral Springs Road

Status: Construction Started

Start Date: 4/27/2015

Completion Date:  8/28/2015

Low Bidder: James Brothers Construction Inc. - Elysian MN

Bid Amount: $529,398.60

2015 Street and Utility Projects – 15001

  • Cherry Street Larch to Aspen Highland

  • 7th Avenue NE - Mineral Springs Road to 26th Street NE

  • Alley— between Broadway and Grove, east of Post Office

  • Alley— between Oak & Walnut south of Harland’s Tire

  • Alley— Oakdale Street to 18th Street SW—West of Cedar

  • Killworth Drive— Brady Boulevard to State Avenue

  • Parking lot between Oak Avenue N and Walnut Avenue N

Status: Bid Awarded

Start Date: 5/18/15

Completion Date:  8/28/2015

Low Bidder: Hesleton Construction Inc. - Faribault, MN

Bid Amount: $663,446.18

2015 Street Overlays – 15002

  • 12th Street SE - Lincoln Ave to Truman Ave
  • 20th Street NE– St. Paul Road to Bigelow Ave

Status: Bid Awarded

Start Date: 5/12/15

Completion Date:  8/21/2015

Low Bidder:  Crane Creek Asphalt - Faribault, MN

Bid Amount: $139,947.88

2015 MSA Pavement Rehabilitation & Overlay – 15003

Pavement Rehabilitation:

  • Austin Road  – Havana Road to 18th Street SE (5/15/15 – 7/26/15)
  • Lincoln Avenue – Main St to Austin Road (6/22/15 – 7/31/15)

Street Overlay:

  • Havana Road Overlay – Grove Ave to Truman Ave (6/22/15 – 8/31/15)

Status: Construction Started

Start Date: 5/12/15

Completion Date:  8/31/2015

Low Bidder:  Crane Creek Asphalt - Faribault, MN

Bid Amount: $640,839.98

2015 Street Maintenance: Crack Seal and Seal Coat - 15005

Location: See Map

Status: Bid Awarded

Start Date: July 2015

Completion Date:  August 2015

Low Bidder

Bid Amount: